Unit 4.1 is about buying a unit that does not yet exist. Because the buyer pays for a building while it is still going up, the Housing Developers (Control and Licensing) Act 1965 and the Housing Developers Rules take the bargaining out of the developer’s hands: the licence, the option, the sale and purchase agreement and the payment schedule are all prescribed. Most of the marks in this unit come from knowing which form applies, what percentage is payable at which stage, and when a period starts to run.
Which sales the Housing Developers Act controls
The Act bites on a “housing development”, which section 2(1) defines as the development of more than four units of housing accommodation. A developer of four units or fewer is outside the licensing regime, which is why the exam so often gives you a unit count in the stem.
A licensed developer holds one of two licences from the Controller of Housing. A sale licence allows construction and the sale of units once the approvals, including Building Plan approval, are in place; a sale licence together with Building Plan approval are the prerequisites for sale. A no-sale licence allows construction only, so units cannot be sold before the project is completed. The criteria differ accordingly: as at URA’s published criteria of August 2024, a sale licence requires paid-up capital from $1 million for a project of 50 units or fewer rising to $4 million for more than 400 units, plus a completed licensed project within the last five years, while a no-sale licence requires only $100,000 of paid-up capital and no track record.
Non-residential developments are outside this Act: the sale of uncompleted commercial and other non-residential strata units by a developer falls under the Sale of Commercial Properties Act 1979.
- Sale licence — may build and sell, once Building Plan approval is obtained
- No-sale licence — may build, but may not sell before completion
- Residential: Housing Developers (Control and Licensing) Act and Rules
- Non-residential strata: Sale of Commercial Properties Act 1979 and Rules
The project account and the developer’s continuing obligations
The buyer’s money is protected by a project account. A licensed developer must open and maintain one with a financial institution for each project, and what may be paid in and taken out is governed by the Housing Developers (Project Account) Rules. The booking fee is paid into that account, and the prescribed option is void if payment is never actually made into it for a reason the developer or its bank is not responsible for. The developer must also submit audited accounts and the auditor’s certification for each project within six months after the close of its financial year, and must use the prescribed forms.
Advertisements are controlled by rule 3, which requires every advertisement to state the developer’s name and licence number, the tenure of the land, the expected date of delivery of vacant possession, the expected date for conveyance of legal title, and the location including the lot and Mukim or Town Subdivision. Rule 6 forbids any suggestion of presidential or family patronage, any suggested connection with a government department or public building, and any attribute the developer cannot genuinely claim.
Enforcement was tightened by URA circular COH 26-01 from 22 May 2026, which allows an errant developer to be disqualified from Government land sales, and sales at unlaunched projects to be suspended, for up to five years.
The Option to Purchase: booking fee, Form 2 and the three-week period
A buyer books a unit by paying a booking fee which, under rule 8, must be not less than 5% and not more than 10% of the purchase price; 5% is the usual market figure. The option must be in Form 2 and is granted on the developer’s acceptance of the booking fee. The developer keeps a register of option holders in Form 1, and the option is neither assignable nor transferable.
Before accepting the booking fee the developer must give the intending purchaser the Form 3 particulars — the unit’s area and floor space breakdown, scaled location, site and floor plans, the specifications, any Controller-approved amendments to the prescribed agreement and the developer’s track record — together with a customer due diligence notice, and must obtain the buyer’s written acknowledgement.
Two periods follow and candidates routinely swap them. Under clause 2.1 of Form 2 the developer must send the buyer the title deed copies and the execution copies of the sale and purchase agreement within 14 days after the option date. Under rule 11(2) and clause 3.1 the option then expires three weeks after the day of that delivery. The buyer exercises by signing all execution copies of the agreement and returning them before expiry, and pays the balance of the 20% deposit, that is 20% of the price less the booking fee, either on exercise or within eight weeks after the option date.
If the option is not exercised, or the buyer gives written notice that he will not exercise it, the option lapses and the developer must refund 75% of the booking fee within four weeks; a quarter of it is therefore not returned. Since 28 September 2020 a developer may not re-issue an option over the same unit to the same buyer within 12 months after the earlier option expires.
Progress payments under the prescribed payment schedule
The sale and purchase agreement must be in Form 4 for a unit that is not a strata lot and Form 5 for a strata lot, and the Singapore Academy of Law acts as stakeholder under both. Amendments not pre-approved by the Controller are null and void even if the buyer agrees to them, which also means a developer cannot rewrite the payment terms: schemes that defer the bulk of the price until after completion do not fit the prescribed schedule for an uncompleted unit.
The schedule in clause 5.1 is the most examined table in this unit, and it is set out below. The first instalment is 20% of the price, inclusive of the booking fee. Each of the six construction stages that follow is payable within 14 days after the buyer receives the developer’s notice that the stage is done, and so is the 25% due on TOP or CSC. The last 15% is paid partly to the developer and partly to the stakeholder, who releases 8% within seven working days after receiving the Certificate of Statutory Completion, with the final 5% on the final payment date.
If the buyer is late, interest runs at 2% a year above the Base Rate, calculated daily. If an instalment stays unpaid for more than 14 days after it is due the developer may treat the agreement as repudiated, but must first give at least 21 days’ written notice; on annulment it may forfeit 20% of the purchase price out of what has been paid, and must refund the balance within 21 days after annulment or the return of vacant possession, whichever is later.
- 20% — signing the agreement, or within 8 weeks of the option date (includes the booking fee)
- 10% foundation; 10% reinforced concrete framework
- 5% partition walls; 5% roofing or ceiling
- 5% door and window frames, wiring, plastering, plumbing; 5% car park, roads and drains
- 25% — Temporary Occupation Permit or Certificate of Statutory Completion
- 15% — the balance, through the stakeholder, on completion and the Certificate of Statutory Completion
Vacant possession, defects liability and floor area shortfall
The Temporary Occupation Permit allows the building to be occupied and vacant possession follows it; the Certificate of Statutory Completion is issued once all requirements are met and triggers the final payment.
The defects liability period is 12 months, and the exam almost always tests when it starts. It runs from the date vacant possession is delivered, or from the fifteenth day after the buyer receives notice of TOP and of completion of the infrastructure works, whichever is earlier. So a buyer notified on 1 June who collects keys on 30 June is working from 16 June, not from the notice date and not from key collection. Defects notified in time must be made good by the developer.
If the final surveyed area of the unit is more than 3% below the area stated in the agreement, the price is reduced for every square metre of shortfall beyond the 3%, not for the whole shortfall. A shortfall of 2% gives no compensation at all.
Completion is driven by a Notice to Complete, given by the date specified in the agreement or three years after delivery of vacant possession, and completion must take place within 14 days after the buyer receives it. The buyer pays six months’ maintenance charges in advance, then quarterly in advance. Where the developer is late in delivering vacant possession the buyer’s right to liquidated damages under the agreement is preserved, and rule 14(2) confirms that a direction from the Controller to complete does not take that right away.
Sub-sales before completion
A buyer who has exercised the option and wants out before completion assigns the benefit of the sale and purchase agreement. The option itself cannot be assigned, so there is nothing to sell until it has been exercised.
On the assignee’s written request the developer must enter into a new agreement with him within three weeks of the request or the assignment, whichever is later, putting the developer and the assignee in the same position as to rights and obligations. If the new agreement would change any term the developer must apply to the Controller within one week, and it may not impose extra terms without the Controller’s written consent. Its charges are capped by rule 16(6) at an administrative fee of not more than $200 plus reimbursement of solicitor’s costs of up to $400, both excluding GST.
Terms to know
- Controller of Housing
- The officer who licenses housing developers and approves any departure from the prescribed option and sale and purchase agreement.
- Sale licence
- A housing developer’s licence permitting both construction and the sale of units, once Building Plan approval has been obtained.
- Project account
- The account with a financial institution that a licensed developer must maintain for each project, into which buyers’ money is paid and out of which withdrawals are controlled by rules.
- Booking fee
- The payment of not less than 5% and not more than 10% of the price on which the developer grants the prescribed Option to Purchase.
- Temporary Occupation Permit (TOP)
- The permit allowing a completed building to be occupied before the Certificate of Statutory Completion is issued.
- Certificate of Statutory Completion (CSC)
- The certificate issued when a building fully complies with the requirements of the authorities; it triggers release of the final instalment.
- Defects liability period
- The 12 months during which the developer must make good defects notified by the buyer.
- Sub-sale
- A sale by a buyer of his rights under the sale and purchase agreement before the project is completed, effected by assignment.
Frequently asked questions
How long does a buyer have to exercise the option on a new launch?
Three weeks, running from the day after the developer delivers the title deed copies and the execution copies of the sale and purchase agreement to the buyer or the buyer’s solicitor. The developer must deliver those documents within 14 days after the option date. The Controller of Housing may approve a different option period.
What happens to the booking fee if the buyer does not proceed?
The option lapses and the developer must refund 75% of the booking fee within four weeks of expiry, or of receiving the buyer’s written notice that he will not exercise the option. The remaining 25% is not returned. The developer may withhold the refund until the buyer shows that any caveat has been withdrawn.
When does the 12-month defects liability period start?
On the earlier of the date vacant possession is delivered and the fifteenth day after the buyer receives notice of the Temporary Occupation Permit and of completion of the roads, drainage, sewerage and utility works. It does not start on the date of the TOP notice itself, and it does not wait for key collection or for the Certificate of Statutory Completion.
Can a developer change the prescribed option or sale and purchase agreement?
Only with the Controller of Housing’s prior written approval, or by adopting an amendment the Controller has already pre-approved. Any other variation is null and void, even if the buyer signed it willingly, so a buyer is not bound by a non-approved clause.
What can a developer charge for a sub-sale before completion?
Rule 16(6) of the Housing Developers Rules caps it at an administrative fee of not more than $200 plus reimbursement of solicitor’s costs of up to $400, both excluding GST. The developer must enter into a new agreement with the assignee within three weeks, and may not impose further terms without the Controller’s written consent.
Official sources
- Housing Developers (Control and Licensing) Act 1965
- Housing Developers Rules (booking fee, Forms 1–5, options, sub-sales)
- URA — housing developers: licences, project account, prescribed forms
- URA — Criteria for a Housing Developer's Licence (August 2024)
- URA — guide for buyers of uncompleted private residential property
- URA circular COH 20-03 — re-issue of options
- URA circular COH 26-01 — measures against errant developers (22 May 2026)
- URA — Sale of Commercial Properties Act and Rules
Practise what you have just read
Free practice questions, with the answer and a full explanation for every one. No account needed.
Disclaimer: All questions on this portal are created to aid candidates in preparing for and passing the Real Estate Salesperson (RES) Examination. They are not official examination questions and are not representative of, endorsed by or affiliated with the Council for Estate Agencies (CEA) or NTUC LearningHub. Laws, rates and policies change — always verify against official sources.